Environment Tasmania says sewage crisis not over with Ti Tree Bend STP storage capacity opening
“Even with increased capacity at Ti Tree Bend the sewage crisis in the Tamar is far from over, but this upgrade is a step in the right direction for water quality.
“With seven out of eight high-capacity sewage treatment plants on the Tamar either failing to comply with their environmental protection notices or spilling under-treated waste into the river, it will take years before Launceston’s waterways are safe from sewage pollution.
“In 2024–25, the Ti Tree Bend sewage treatment plant released more under-treated sewage than any other plant in the state, with over 338 million litres flowing directly into the Tamar. TasWater estimates the new 10-megalitre storage facility will reduce these events by only 60%.
“Even with these upgrades, sewage pollution events, known as bypass events, are still likely at overloaded plants for years to come. Prospect Vale sewage treatment plant, which released over 27 million litres of under-treated sewage above Cataract Gorge in 2024–25 alone, isn’t due to be replaced until the end of 2028.
“While the Launceston Sewer Transformation continues over the next decade, it’s critical that residents and visitors using the Tamar are told when these pollution events happen.
“That’s why Environment Tasmania is calling for Event Duration Monitors at all high-capacity sewage treatment plants across Tasmania, so the public can be alerted in real time to sewage pollution and protect their health when using our waterways, while these critical upgrades continue.”
All comments attributed to Lucy Tremain, Freshwater Campaigner, Environment Tasmania